Takeoff: steel vs. wood framing

Steel vs. wood calculator

A planning tool, not a quote. It compares three ways to frame the same building: stick-built wood, wood trusses, and panelized steel. For each it adds up materials, framing labor, waste and haul-off, crane and equipment, and framing time at your own cost per day. Every number shows its source.

Planning estimates

These are planning ranges built from published studies and cost surveys, shown with their sources below. Steel package and schedule figures stay estimates until the manufacturer confirms them in writing for your plans. Your own quote always replaces them.

Inputs

Building type
Stories
What to compare

What each extra day of framing costs you: loan interest, equipment rental, supervision, other trades waiting. Crew pay is counted in Labor.

Have real quotes? Enter them (optional)

Your wood price narrows the ranges; steel and wood trusses keep the sourced ratio to it. A steel quote replaces the steel estimate.

Compared with a normal market. When lumber spikes, wood costs more and the gap to steel narrows.

Result

Planning estimates

Stick-built wood

Studs, joists and rafters cut and nailed together on site.

Materials
$14,100 to $45,800
Framing labor
$5,600 to $13,000
Waste and haul-off
$1,800 to $2,700
Crane and equipment
$0 to $0
Framing time 3 to 10 days at $200/day
$600 to $2,000
Total
$22,100 to $63,500

Wood trusses

Site-built walls with factory wood roof and floor trusses, usually set by crane.

Materials
$14,100 to $45,800
Framing labor
$4,500 to $10,700
Waste and haul-off
$1,200 to $1,800
Crane and equipment
$600 to $1,600
Framing time 3 to 9 days at $200/day
$600 to $1,800
Total
$21,000 to $61,700

Panelized steel

Factory-built steel wall panels and trusses, assembled on site.

Materials
$16,400 to $69,000
Framing labor
$4,500 to $13,000
Waste and haul-off
$600 to $1,800
Crane and equipment
$0 to $1,600
Extra wall insulation where the energy code asks
$0 to $2,900
Framing time 1.5 to 10 days at $200/day
$300 to $2,000
Total
$21,800 to $90,300
Panelized steel minus stick-built wood-$300 to +$26,800
Panelized steel minus wood trusses+$800 to +$28,600

One story on a slab has no framed floor, so floors add nothing here.

Quantities and cost by part
Framing quantities and material and labor ranges by part and method
PartQty (sq ft)Stick-built woodWood trussesPanelized steel
Roof 2,236 sq ft2,236Materials $5,600 to $18,100 / Labor $2,200 to $5,100Materials $5,600 to $18,100 / Labor $1,800 to $4,200Materials $6,500 to $27,300 / Labor $1,800 to $5,100
Walls 3,415 sq ft3,415Materials $8,500 to $27,700 / Labor $3,400 to $7,900Materials $8,500 to $27,700 / Labor $2,700 to $6,500Materials $9,900 to $41,700 / Labor $2,700 to $7,900

Estimate only. Your manufacturer will provide actual pricing.

How this is calculated

Three ways to frame the same building: stick-built wood, wood trusses over stick-built walls, and panelized light gauge steel. For each, the calculator adds materials, framing labor, waste and haul-off, crane and equipment, extra wall insulation (steel only, where the energy code asks for it) and framing time (framing days times your own cost per day). It excludes foundation, roofing, insulation in the cavities, finishes, permits, engineering fees and delivery unless your quotes include them.

  • Footprint is treated as a rectangle twice as long as it is wide, so perimeter = 6 x sqrt(footprint / 2).
  • Sloped roof area = footprint x sqrt(1 + (pitch / 12)^2). Overhangs are not included.
  • Exterior wall area = perimeter x wall height x stories, plus the interior wall allowance for the building type. Openings are not deducted.
  • Framed floor area = footprint x (stories - 1). The ground floor is assumed to be a slab.
  • Materials and labor = the quantities above x a low and a high rate for each method. Where no source splits a price by roof, walls and floors, the same rate is used for all three, so the total is what the sources support.
  • Waste and haul-off, crane and equipment are per 1,000 sq ft of floor area framed. Extra wall insulation is per sq ft of exterior wall, applies to steel only, and applies only where the energy-code path asks for it, so its low end is zero. Wood lumber price moves wood materials only.
  • Framing days = quantity / 1,000 x crew days per 1,000 sq ft, rounded to the nearest half day. Time cost = framing days x your cost per day (loan interest, equipment rental, supervision, other trades waiting). Crew pay is in Labor, so nothing is counted twice.
  • Dollar amounts are rounded to the nearest $100 and days to the nearest half day.

How to read it: in every published comparison we found, a steel framing package costs more than wood in a normal lumber market, and the case for steel is schedule, predictability and fewer site problems. How much time a panelized steel frame saves on a house is the least-documented number here, so it is a wide range until the manufacturer confirms it in writing. Your own quote always replaces these numbers.

Notes: assumptions used

ItemRangeUnitStatusSource
Materials: roof, stick-built wood2.5–8.1USD per sq ft of sloped roof areaPlanning estimateNAHB Cost of Constructing a Home 2024 (framing group $26.82 per sq ft of finished area, national, 41 builders), checked 2026-10-11
Materials: roof, wood trusses2.5–8.1USD per sq ft of sloped roof areaPlanning estimateNAHB Cost of Constructing a Home 2024 (framing group $26.82 per sq ft of finished area, national, 41 builders), checked 2026-10-11
Materials: roof, panelized steel2.9–12.2USD per sq ft of sloped roof areaPlanning estimateR.A. Smith for the Steel Framing Industry Association (steel trade group), cost study, 2020 (framing-only +21%), checked 2026-10-11
Materials: walls, stick-built wood2.5–8.1USD per sq ft of framed wall areaPlanning estimateNAHB Cost of Constructing a Home 2024 (framing group $26.82 per sq ft of finished area, national, 41 builders), checked 2026-10-11
Materials: walls, wood trusses2.5–8.1USD per sq ft of framed wall areaPlanning estimateNAHB Cost of Constructing a Home 2024 (framing group $26.82 per sq ft of finished area, national, 41 builders), checked 2026-10-11
Materials: walls, panelized steel2.9–12.2USD per sq ft of framed wall areaPlanning estimateR.A. Smith for the Steel Framing Industry Association (steel trade group), cost study, 2020 (framing-only +21%), checked 2026-10-11
Materials: floors, stick-built wood2.5–8.1USD per sq ft of framed floor areaPlanning estimateNAHB Cost of Constructing a Home 2024 (framing group $26.82 per sq ft of finished area, national, 41 builders), checked 2026-10-11
Materials: floors, wood trusses2.5–8.1USD per sq ft of framed floor areaPlanning estimateNAHB Cost of Constructing a Home 2024 (framing group $26.82 per sq ft of finished area, national, 41 builders), checked 2026-10-11
Materials: floors, panelized steel2.9–12.2USD per sq ft of framed floor areaPlanning estimateR.A. Smith for the Steel Framing Industry Association (steel trade group), cost study, 2020 (framing-only +21%), checked 2026-10-11
Framing labor: roof, stick-built wood1–2.3USD of framing labor per sq ft of sloped roof areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing labor: roof, wood trusses0.8–1.9USD of framing labor per sq ft of sloped roof areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing labor: roof, panelized steel0.8–2.3USD of framing labor per sq ft of sloped roof areaPlanning estimateHUD PD&R / NAHB Research Center, Steel vs. Wood Cost Comparison, Beaufort SC, 2002, checked 2026-10-11
Framing labor: walls, stick-built wood1–2.3USD of framing labor per sq ft of framed wall areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing labor: walls, wood trusses0.8–1.9USD of framing labor per sq ft of framed wall areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing labor: walls, panelized steel0.8–2.3USD of framing labor per sq ft of framed wall areaPlanning estimateHUD PD&R / NAHB Research Center, Steel vs. Wood Cost Comparison, Beaufort SC, 2002, checked 2026-10-11
Framing labor: floors, stick-built wood1–2.3USD of framing labor per sq ft of framed floor areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing labor: floors, wood trusses0.8–1.9USD of framing labor per sq ft of framed floor areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing labor: floors, panelized steel0.8–2.3USD of framing labor per sq ft of framed floor areaPlanning estimateHUD PD&R / NAHB Research Center, Steel vs. Wood Cost Comparison, Beaufort SC, 2002, checked 2026-10-11
Framing time: roof, stick-built wood0.5–1.8crew days per 1,000 sq ft of sloped roof areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing time: roof, wood trusses0.5–1.6crew days per 1,000 sq ft of sloped roof areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing time: roof, panelized steel0.3–1.8crew days per 1,000 sq ft of sloped roof areaPlanning estimateUNSW, MDPI Buildings 15(14), 2025 (prefab steel panels vs on-site steel; baseline is not wood), checked 2026-10-11
Framing time: walls, stick-built wood0.5–1.8crew days per 1,000 sq ft of framed wall areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing time: walls, wood trusses0.5–1.6crew days per 1,000 sq ft of framed wall areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing time: walls, panelized steel0.3–1.8crew days per 1,000 sq ft of framed wall areaPlanning estimateUNSW, MDPI Buildings 15(14), 2025 (prefab steel panels vs on-site steel; baseline is not wood), checked 2026-10-11
Framing time: floors, stick-built wood0.5–1.8crew days per 1,000 sq ft of framed floor areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing time: floors, wood trusses0.5–1.6crew days per 1,000 sq ft of framed floor areaPlanning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Framing time: floors, panelized steel0.3–1.8crew days per 1,000 sq ft of framed floor areaPlanning estimateUNSW, MDPI Buildings 15(14), 2025 (prefab steel panels vs on-site steel; baseline is not wood), checked 2026-10-11
Waste and haul-off, stick-built wood900–1350USD per 1,000 sq ft of floor area framed (dumpsters and haul-off of framing scrap and packaging)Planning estimateOffsite Builder 2022 and ProBuilder 2021 (3 hauls stick vs 1 precut) with dumpsters.com Oct 2026 prices ($588 to $642 per haul in SE cities), checked 2026-10-11
Waste and haul-off, wood trusses600–900USD per 1,000 sq ft of floor area framed (dumpsters and haul-off of framing scrap and packaging)Planning estimateOffsite Builder 2022 and ProBuilder 2021 (3 hauls stick vs 1 precut) with dumpsters.com Oct 2026 prices ($588 to $642 per haul in SE cities), checked 2026-10-11
Waste and haul-off, panelized steel300–900USD per 1,000 sq ft of floor area framed (dumpsters and haul-off of framing scrap and packaging)Planning estimateOffsite Builder 2022 and ProBuilder 2021 (3 hauls stick vs 1 precut) with dumpsters.com Oct 2026 prices ($588 to $642 per haul in SE cities), checked 2026-10-11
Crane and equipment, stick-built wood0–0USD per 1,000 sq ft of floor area framed (crane or boom truck for trusses, plus tools and fuel)Planning estimateHolt, Anzlovar and Welsh, The Professional Constructor 46(2), 2021 (builder-reported framing labor and timed same-plan studies), checked 2026-10-11
Crane and equipment, wood trusses310–800USD per 1,000 sq ft of floor area framed (crane or boom truck for trusses, plus tools and fuel)Planning estimateLimehouse & Sons, Ladson SC, published boom-truck rates ($145 to $185 per hour, 4-hour minimum), checked 2026-10-11
Crane and equipment, panelized steel0–800USD per 1,000 sq ft of floor area framed (crane or boom truck for trusses, plus tools and fuel)Planning estimateLimehouse & Sons, Ladson SC, published boom-truck rates ($145 to $185 per hour, 4-hour minimum), checked 2026-10-11
Extra wall insulation, stick-built wood0–0USD per sq ft of exterior wall (continuous exterior insulation)Planning estimateHome Innovation Research Labs for NAHB, 2021 IECC cost analysis (R-10 continuous foam $1.32 to $1.72 per sq ft of wall), checked 2026-10-11
Extra wall insulation, wood trusses0–0USD per sq ft of exterior wall (continuous exterior insulation)Planning estimateHome Innovation Research Labs for NAHB, 2021 IECC cost analysis (R-10 continuous foam $1.32 to $1.72 per sq ft of wall), checked 2026-10-11
Extra wall insulation, panelized steel0–1.72USD per sq ft of exterior wall (continuous exterior insulation)Planning estimateHome Innovation Research Labs for NAHB, 2021 IECC cost analysis (R-10 continuous foam $1.32 to $1.72 per sq ft of wall), checked 2026-10-11
Starting cost per day$200USD per day of framing (starting value; visitors can change it)Example valueStarting value only. Enter your own: construction-loan interest, rentals, supervision and other trades waiting.
Regional factor (all states)1multiplier applied to materials and laborExample valueNo adjustment: the sourced ranges are already Southeast or national, and no regional split exists in the sources.
Interior wall allowance1 / 0.5 / 0 / 0.5house / barndominium / garage or shop / commercialExample valueEXAMPLE VALUE

Schedule: non-price factors

What you get for the difference

Price is one column. These are the others, with sources. Where the evidence is mixed, we say so. Sources marked as trade groups come from an industry with an interest in one material.

FactorWhat the sources sayFavorsEvidenceSources
Up-front costSteel framing generally costs more than wood up front. In a HUD study from the early 1990s, steel walls cost about 7% more than wood and the steel roof about 36% more. In a 2002 HUD demonstration in Beaufort, SC, the steel framing package cost about 42% more, partly blamed on an inexperienced steel crew. Both studies are old. Treat them as direction, not current prices.Woodconsistent
Straightness and dimensional consistencyWood shrinks and swells as its moisture content changes, which can lead to warping, bowing and twisting. Cold-formed steel does not change size with moisture.Steelconsistent
Rot, mold and termitesSteel is not food for decay fungi or termites. Steel relies on its galvanized (zinc) coating against corrosion, and coastal or wet sites may call for a heavier coating. Subterranean termites are more common in southern states. Ask the manufacturer what coating weight they specify near the coast.Steelconsistent
Combustibility and fireCold-formed steel is a noncombustible material. Fire-resistance ratings belong to tested assemblies (framing plus gypsum board and other layers), and wood-frame assemblies can also be rated. We make no fire-rating claim. Ratings come from the tested assembly your designer specifies.Mixedconsistent
Insulation and energySteel conducts heat far more than wood. Energy codes require extra insulation on steel-framed walls, usually a layer of continuous exterior insulation, to perform like a wood wall. Budget for continuous insulation when comparing prices.Woodconsistent
Installation speed and crew skillSite-built steel took about the same framer hours as wood once a crew had learned it, and 30% to 50% more on a first job (HUD field studies). Factory-built panels and trusses cut site hours in both materials: prefabricated wall panels used 27% to 54% fewer wall hours in timed wood studies, and prefabricated steel panels took 4 working days against 13 for on-site steel framing in a 2025 university study. No study yet measures panelized steel against wood on houses. Ask whether your crew has framed steel before, and ask the manufacturer for a documented schedule on a project like yours.Mixedmixed
Handling and deliverySteel members arrive straight and uniform and can be ordered cut to length, usually at extra cost. Steel scrap is recyclable. Weight per foot depends on gauge: a common 2x4-size steel stud weighs about the same as a 2x4. Weight savings claims depend on the gauge used.Mixedmixed
InsuranceInsurers rate buildings by construction class, and the class depends on the whole building, not only the studs. We found no independent public data showing lower homeowner premiums for steel-framed houses. Ask your insurance agent before counting on a savings.Dependsweak
StrengthNeither material is stronger in every case. Load capacity depends on member size, wood species and grade or steel gauge, height and bracing. Both are engineered to carry the loads your project requires. The manufacturer's engineering sets member sizes for your loads.Dependsconsistent
Waste and dumpstersPre-cut and panelized framing leaves far less scrap on the job: a measured pair of 2,900 sq ft houses produced about a 15-yard dumpster of framing waste with stick framing against a few trash cans with components, and builders typically need 3 dumpster hauls for stick framing against 1 for precut. Steel scrap is also recyclable. Other trades still need a dumpster for drywall, packaging and cladding. Measured steel waste data barely exists. The commonly quoted '2% steel against 20% wood' has no source; the best-supported wood estimating range is 8% to 15%.Mixedconsistent
Lumber price swingsWood framing cost moves with the lumber market, while steel framing is priced from a coil-based index that moves differently. In a normal market steel framing packages price above wood; at a lumber price spike a steel-industry study found the steel package about 24% below wood. Softwood lumber prices stood at about half of their 2021 peak in 2026, and tariffs and duties on Canadian lumber are a price risk. The 24% figure comes from a steel trade group study at peak 2020 prices. Use the lumber price setting in the calculator to see the effect.Dependsmixed

Sources checked 2026-10-11. Confirm code, load and permit requirements with your local building department and the engineer of record.